Project Name: Chilled Water Distribution System Phase 7
Location: Fort Gordon, GA
Contract Amount: $6.9M
Size: Not Applicable
CCCI PN: 367
Owner: U.S. Army Corps of Engineers
Design Professional: Stanley Consultants
Project Description: Copper Construction Company, Inc. (CCCI) served as a subcontractor on this underground piping project that included the installation of new underground chilled water piping, trenching, repairs to sidewalks, parking lots, road crossings, new building risers, erosion control, grassing, and the design of the 2400 block.